Weekly Update 10/26/26

Last week the contractor worked on installing construction entrances at Cleland Dr., S. Estes Dr., Ridgefield Rd., and Willow Dr. They cleared some trees, mulched, and continued installing the silt fence.

This week will be much of the same. They are expected to install the construction entrance at Walnut St. and clearing trees and brush between Cleland Dr., and S. Estes Dr.

The Town and contractor continue to ask for the public's adherence to the trail closure signs and barricades. This is important to keep everyone safe.