Weekly update 11/02/26

Last week, the contractor began clearing trees and brush at the construction entrances at Cleland Drive and Walnut Street. This week, we expect our contractor to continue tree clearing and complete the installation of the construction entrances, including a silt fence placed from Walnut Street to Willow Drive.

Depending on equipment scheduling, a lane closure along Fordham Boulevard may be required to enable the clearing of large trees from Estes Drive to Ridgefield Road. We will keep this page updated on any lane closures.

The Town and contractor continue to ask for the public's adherence to the trail closure signs and barricades, as well as any future lane closures. This is important to keep everyone safe.