Fordham Boulevard Sidepath
This project upgrades the existing multi-modal (pedestrian and bicycle) sidepath along Fordham Boulevard between Cleland Drive and Ridgefield Road by the Rainbow Soccer fields from asphalt to concrete and will construct a new concrete sidepath between Ridgefield Road and Willow Drive.
The project also includes additional traffic-calming systems, landscaping, and a noise reducing fence system along the path between Ridgefield Rd. and Willow Dr.
It’s a federally funded project with an original allocation in 2016 and subsequent funding in 2024. The construction bids received in 2023 were higher than the funding allowed. The Town sought additional funding, then Tropical Storm Chantal required revisions to the project design to address site damage and mitigate similar damage in the future.
This project upgrades the existing multi-modal (pedestrian and bicycle) sidepath along Fordham Boulevard between Cleland Drive and Ridgefield Road by the Rainbow Soccer fields from asphalt to concrete and will construct a new concrete sidepath between Ridgefield Road and Willow Drive.
The project also includes additional traffic-calming systems, landscaping, and a noise reducing fence system along the path between Ridgefield Rd. and Willow Dr.
It’s a federally funded project with an original allocation in 2016 and subsequent funding in 2024. The construction bids received in 2023 were higher than the funding allowed. The Town sought additional funding, then Tropical Storm Chantal required revisions to the project design to address site damage and mitigate similar damage in the future.
-
Weekly update 11/09/26
Share Weekly update 11/09/26 on Facebook Share Weekly update 11/09/26 on X (formerly Twitter) Share Weekly update 11/09/26 on Linkedin Email Weekly update 11/09/26 linkLast week the contractor continued clearing and mulching between Walnut St and Willow Dr.
This week, the contractor will install the remaining construction entrance on Walnut St and the remaining silt fence. The contractor will also begin grading from Cleland Dr to the bridge, subject to equipment availability.
The Fordham Boulevard sidepath is now continuously closed to allow our contractors to continue construction work. In addition, there may be intermittent closure of the right lane of Fordham Blvd so crews can do tree work adjacent to the road.
The Town and contractor continue to ask for the public's adherence to trail and road closures. This is important to keep everyone safe while construction activities are underway.
Last week the contractor continued clearing and mulching between Walnut St and Willow Dr.
This week, the contractor will install the remaining construction entrance on Walnut St and the remaining silt fence. The contractor will also begin grading from Cleland Dr to the bridge, subject to equipment availability.
The Fordham Boulevard sidepath is now continuously closed to allow our contractors to continue construction work. In addition, there may be intermittent closure of the right lane of Fordham Blvd so crews can do tree work adjacent to the road.
The Town and contractor continue to ask for the public's adherence to trail and road closures. This is important to keep everyone safe while construction activities are underway.
-
Weekly update 11/02/26
Share Weekly update 11/02/26 on Facebook Share Weekly update 11/02/26 on X (formerly Twitter) Share Weekly update 11/02/26 on Linkedin Email Weekly update 11/02/26 linkLast week, the contractor began clearing trees and brush at the construction entrances at Cleland Drive and Walnut Street. This week, we expect our contractor to continue tree clearing and complete the installation of the construction entrances, including a silt fence placed from Walnut Street to Willow Drive.
Depending on equipment scheduling, a lane closure along Fordham Boulevard may be required to enable the clearing of large trees from Estes Drive to Ridgefield Road. We will keep this page updated on any lane closures.
The Town and contractor continue to ask for the public's adherence to the trail closure signs and barricades, as well as any future lane closures. This is important to keep everyone safe.
Last week, the contractor began clearing trees and brush at the construction entrances at Cleland Drive and Walnut Street. This week, we expect our contractor to continue tree clearing and complete the installation of the construction entrances, including a silt fence placed from Walnut Street to Willow Drive.
Depending on equipment scheduling, a lane closure along Fordham Boulevard may be required to enable the clearing of large trees from Estes Drive to Ridgefield Road. We will keep this page updated on any lane closures.
The Town and contractor continue to ask for the public's adherence to the trail closure signs and barricades, as well as any future lane closures. This is important to keep everyone safe.
-
Weekly Update 10/26/26
Share Weekly Update 10/26/26 on Facebook Share Weekly Update 10/26/26 on X (formerly Twitter) Share Weekly Update 10/26/26 on Linkedin Email Weekly Update 10/26/26 linkLast week the contractor worked on installing construction entrances at Cleland Dr., S. Estes Dr., Ridgefield Rd., and Willow Dr. They cleared some trees, mulched, and continued installing the silt fence.
This week will be much of the same. They are expected to install the construction entrance at Walnut St. and clearing trees and brush between Cleland Dr., and S. Estes Dr.
The Town and contractor continue to ask for the public's adherence to the trail closure signs and barricades. This is important to keep everyone safe.
Last week the contractor worked on installing construction entrances at Cleland Dr., S. Estes Dr., Ridgefield Rd., and Willow Dr. They cleared some trees, mulched, and continued installing the silt fence.
This week will be much of the same. They are expected to install the construction entrance at Walnut St. and clearing trees and brush between Cleland Dr., and S. Estes Dr.
The Town and contractor continue to ask for the public's adherence to the trail closure signs and barricades. This is important to keep everyone safe.
-
Weekly update 10/19/26
Share Weekly update 10/19/26 on Facebook Share Weekly update 10/19/26 on X (formerly Twitter) Share Weekly update 10/19/26 on Linkedin Email Weekly update 10/19/26 linkWe will be providing weekly updates on the Fordham Sidepath construction as it progresses. This week the contractor will continue installing construction entrances between Ridgefield Rd. and Willow Dr. They will continue mulching and clearing necessary to install the silt fence. There will be a crane on site on Thursday (10/22) to cut several larger trees.
For now, the existing sidepath will be closed daily during work and will open in the evenings when the contractor is done for the day. Eventually the path will be closed day and night, and we will post here when we have that date. In order to keep everyone safe, we ask that the public stay off the path when it's closed.
We will be providing weekly updates on the Fordham Sidepath construction as it progresses. This week the contractor will continue installing construction entrances between Ridgefield Rd. and Willow Dr. They will continue mulching and clearing necessary to install the silt fence. There will be a crane on site on Thursday (10/22) to cut several larger trees.
For now, the existing sidepath will be closed daily during work and will open in the evenings when the contractor is done for the day. Eventually the path will be closed day and night, and we will post here when we have that date. In order to keep everyone safe, we ask that the public stay off the path when it's closed.
-
Tree clearing to begin 10/15
Share Tree clearing to begin 10/15 on Facebook Share Tree clearing to begin 10/15 on X (formerly Twitter) Share Tree clearing to begin 10/15 on Linkedin Email Tree clearing to begin 10/15 linkThe Fordham Sidepath contractor will begin clearing trees along the project corridor on Thursday, October 15th. Initial clearing will occur between Cleland Drive and the bridge over Bolin Creek and will last until mid-week next week. Existing trail users should find alternate routes, as the existing trail between Cleland Drive and Ridgefield Road will be closed during working hours for the foreseeable future. The contractor will open the trail at the end of the day when it's safe to do so.

The Fordham Sidepath contractor will begin clearing trees along the project corridor on Thursday, October 15th. Initial clearing will occur between Cleland Drive and the bridge over Bolin Creek and will last until mid-week next week. Existing trail users should find alternate routes, as the existing trail between Cleland Drive and Ridgefield Road will be closed during working hours for the foreseeable future. The contractor will open the trail at the end of the day when it's safe to do so.

-
Staking and Construction Set to Begin
Share Staking and Construction Set to Begin on Facebook Share Staking and Construction Set to Begin on X (formerly Twitter) Share Staking and Construction Set to Begin on Linkedin Email Staking and Construction Set to Begin linkLanier Construction, the firm hired by the Town to construct the Fordham Sidepath, will begin staking the perimeter of the project limits as early as this Friday, September 18th. Lanier anticipates breaking ground on the project as soon as September 28th and construction will continue for about a year. No traffic impacts are expected on Fordham Boulevard, and occasional temporary lane closures on the intersecting side streets will be advertised ahead of time. The existing asphalt sidepath between Cleland Drive and Ridgefield Road is not expected to be passable during construction.
Please check this page for updates as construction progresses.
Lanier Construction, the firm hired by the Town to construct the Fordham Sidepath, will begin staking the perimeter of the project limits as early as this Friday, September 18th. Lanier anticipates breaking ground on the project as soon as September 28th and construction will continue for about a year. No traffic impacts are expected on Fordham Boulevard, and occasional temporary lane closures on the intersecting side streets will be advertised ahead of time. The existing asphalt sidepath between Cleland Drive and Ridgefield Road is not expected to be passable during construction.
Please check this page for updates as construction progresses.
-
Construction Scheduled to Begin this Fall
Share Construction Scheduled to Begin this Fall on Facebook Share Construction Scheduled to Begin this Fall on X (formerly Twitter) Share Construction Scheduled to Begin this Fall on Linkedin Email Construction Scheduled to Begin this Fall linkThe sidepath construction contract is approved, and work will start in late September or early October.
The sidepath construction contract is approved, and work will start in late September or early October.
-
Summer 2026 Update
Share Summer 2026 Update on Facebook Share Summer 2026 Update on X (formerly Twitter) Share Summer 2026 Update on Linkedin Email Summer 2026 Update linkThe Town received five construction cost bids on June 2, 2026, and we are working on the approval of the apparent low bidder's construction contract. Construction is planned to commence this fall.
The Town received five construction cost bids on June 2, 2026, and we are working on the approval of the apparent low bidder's construction contract. Construction is planned to commence this fall.
-
Request for Construction Bids Released
Share Request for Construction Bids Released on Facebook Share Request for Construction Bids Released on X (formerly Twitter) Share Request for Construction Bids Released on Linkedin Email Request for Construction Bids Released linkThe Town’s request for construction bids went out on Tuesday, May 12, and the bids are due at 2:00pm on June 2, 2026.
The Town’s request for construction bids went out on Tuesday, May 12, and the bids are due at 2:00pm on June 2, 2026.
-
Mobility and Greenways Manager
BW -
Principal Planner/Project Manager
MP
-
Fall/Winter 2017
Fordham Boulevard Sidepath has finished this stageSolicitation and Procurement Professional Services (Engineering): Planning and Design
-
Winter/Summer 2018
Fordham Boulevard Sidepath has finished this stagePlanning and Preliminary Design
-
Winter 2019 - Spring 2020
Fordham Boulevard Sidepath has finished this stageDesign and Construction Documents
-
Spring 2020 - Winter 2021
Fordham Boulevard Sidepath has finished this stageDesign and Construction Documents Permitting, Regulatory and Public Review
-
Spring 2022
Fordham Boulevard Sidepath has finished this stageConstruction Bidding
-
May 2026
Fordham Boulevard Sidepath has finished this stageComplete Design Revisions
-
May 2026
Fordham Boulevard Sidepath has finished this stageConstruction Bidding
-
September 2026 – Winter 2027
Fordham Boulevard Sidepath is currently at this stageConstruction
-
Winter 2027
this is an upcoming stage for Fordham Boulevard SidepathProjected Completion Date