Fordham Boulevard Sidepath

Share Fordham Boulevard Sidepath on Facebook Share Fordham Boulevard Sidepath on X (formerly Twitter) Share Fordham Boulevard Sidepath on Linkedin Email Fordham Boulevard Sidepath link
Map of sidepath between Fordham Blvd. and Hickory Drive

This project upgrades the existing multi-modal (pedestrian and bicycle) sidepath along Fordham Boulevard between Cleland Drive and Ridgefield Road by the Rainbow Soccer fields from asphalt to concrete and will construct a new concrete sidepath between Ridgefield Road and Willow Drive.

The project also includes additional traffic-calming systems, landscaping, and a noise reducing fence system along the path between Ridgefield Rd. and Willow Dr.

It’s a federally funded project with an original allocation in 2016 and subsequent funding in 2024. The construction bids received in 2023 were higher than the funding allowed. The Town sought additional funding, then Tropical Storm Chantal required revisions to the project design to address site damage and mitigate similar damage in the future.

This project upgrades the existing multi-modal (pedestrian and bicycle) sidepath along Fordham Boulevard between Cleland Drive and Ridgefield Road by the Rainbow Soccer fields from asphalt to concrete and will construct a new concrete sidepath between Ridgefield Road and Willow Drive.

The project also includes additional traffic-calming systems, landscaping, and a noise reducing fence system along the path between Ridgefield Rd. and Willow Dr.

It’s a federally funded project with an original allocation in 2016 and subsequent funding in 2024. The construction bids received in 2023 were higher than the funding allowed. The Town sought additional funding, then Tropical Storm Chantal required revisions to the project design to address site damage and mitigate similar damage in the future.

  • Staking and Construction Set to Begin

    Share Staking and Construction Set to Begin on Facebook Share Staking and Construction Set to Begin on X (formerly Twitter) Share Staking and Construction Set to Begin on Linkedin Email Staking and Construction Set to Begin link

    Lanier Construction, the firm hired by the Town to construct the Fordham Sidepath, will begin staking the perimeter of the project limits as early as this Friday, September 18th. Lanier anticipates breaking ground on the project as soon as September 28th and construction will continue for about a year. No traffic impacts are expected on Fordham Boulevard, and occasional temporary lane closures on the intersecting side streets will be advertised ahead of time. The existing asphalt sidepath between Cleland Drive and Ridgefield Road is not expected to be passable during construction.

    Please check this page for updates as construction progresses.

    Lanier Construction, the firm hired by the Town to construct the Fordham Sidepath, will begin staking the perimeter of the project limits as early as this Friday, September 18th. Lanier anticipates breaking ground on the project as soon as September 28th and construction will continue for about a year. No traffic impacts are expected on Fordham Boulevard, and occasional temporary lane closures on the intersecting side streets will be advertised ahead of time. The existing asphalt sidepath between Cleland Drive and Ridgefield Road is not expected to be passable during construction.

    Please check this page for updates as construction progresses.

  • Construction Scheduled to Begin this Fall

    Share Construction Scheduled to Begin this Fall on Facebook Share Construction Scheduled to Begin this Fall on X (formerly Twitter) Share Construction Scheduled to Begin this Fall on Linkedin Email Construction Scheduled to Begin this Fall link

    The sidepath construction contract is approved, and work will start in late September or early October.

    The sidepath construction contract is approved, and work will start in late September or early October.

  • Summer 2026 Update

    Share Summer 2026 Update on Facebook Share Summer 2026 Update on X (formerly Twitter) Share Summer 2026 Update on Linkedin Email Summer 2026 Update link

    The Town received five construction cost bids on June 2, 2026, and we are working on the approval of the apparent low bidder's construction contract. Construction is planned to commence this fall.

    The Town received five construction cost bids on June 2, 2026, and we are working on the approval of the apparent low bidder's construction contract. Construction is planned to commence this fall.

  • Request for Construction Bids Released

    Share Request for Construction Bids Released on Facebook Share Request for Construction Bids Released on X (formerly Twitter) Share Request for Construction Bids Released on Linkedin Email Request for Construction Bids Released link

    The Town’s request for construction bids went out on Tuesday, May 12, and the bids are due at 2:00pm on June 2, 2026.

    The Town’s request for construction bids went out on Tuesday, May 12, and the bids are due at 2:00pm on June 2, 2026.

Page last updated: 15 Sep 2026, 04:25 PM